Set up a Workflow to a Submittal

Modified on Tue, 12 Nov at 5:25 AM

The general contractor is the hub for all subcontractors, architects, engineers, owners, and other parties involved in a construction project. Any communication between the parties can only be routed appropriately by the GC. Hence, it becomes GC's responsibility to duly forward a submittal from the creator to the responsible parties for processing. Once the workflow is set up, Linarc automatically moves the item to respective companies in successive steps for their actions as per the workflow.

The submittal workflow governs the routing of submittal to respective parties at successive stages in the order. For example, a submittal created by a SC is routed, the submittal manager of the GC reviews and sets up a suitable workflow for the submittal.

The submittal workflow governs the routing of the submittal to respective parties at successive stages in the order. 

  • Linarc allows the company admins to create and maintain custom workflow templates with different sequences of actions, the company type responsible for the action, and the maximum permissible days for each step. 
  • Any company, may it be the Owner, GC, SC, or the Architect, can be set as the responsible party to respond to a submittal in different templates. 
  • The submittal workflow templates, defined at the company level, are available for selection to apply to the submittals pertaining to all the company's projects. submittal workflow managers from the company can use the template appropriate to a submittal depending on its creator, the nature of the submission, and who to respond.
  • At any stage of the flow of submittal, the manager can edit the workflow to change the responders and due dates of the current and the pending steps.    
  • Linarc also provides the versatility of dynamically adding more steps to the primary workflow of a submittal. The parties assigned to respond, review, and approve a submittal can add ad-hoc steps to dynamically route the item to other parties, for example, the creator, should they need any further clarifications or reviews. Once the additional steps are completed, the submittal returns to the original assignee as per the primary workflow to proceed further. The ad-hoc workflow steps can be added any number of times within the lifecycle of a submittal.
Roles and Permissions:
  • Only users with roles having 'Create,' 'Maintain,' or 'Manage' permission enabled for the submittal module can set up the workflow.
  • You can view the persons designated with the above permissions for a project in the 'Project'> 'My Team'> 'Members'> 'Workflow' screen.

You can perform an initial review of the submittals and move forward with setting up a workflow for legitimate ones.

  • Forward for Review and Approval - If the submittal deserves clarifications from other stakeholders, you can set up a workflow and forward it to the next step, typically to the design team. 
  • Respond- Depending on the context, you can respond to the submittal.  You can still set up a workflow and forward the submittal to the responsible party for the responses. See Submit a Submittal for more details.
  • Delete - If you can answer the submittal through other communication means like the built-in collaboration or if the submittal is trivial, you can reject the submittal by deleting it. See Delete a submittal for more details

To open the submittal

  • Ensure that you are in the management console of the project
  • Click the app launcher  , select 'Documents'
  • Click 'Submittals' on the top, then select 'Boards' on the left
  • Open the submittal from the 'Drafts' or 'In Progress' column
  • Drafts: Displays submittals created by you and members of your company.
  • In Progress: Shows submittals from other companies. Submittals that require your attention are marked as 'Open' and tagged with 'You' in blue, indicating they are assigned to you

To set up a workflow for the submittal

  • Click the 'Workflow' tab
  • Choose a template depending on the creator, the context, and the entities responsible for various actions on the submittal.

Once chosen, the sequence of steps, with the actions and the responsible company types in each step shown as a list.

Note: The 'Create' step is completed by default and will appear in the list of actions once the workflow is saved. You can only configure the responsible companies and set durations for each action in the subsequent steps.
  • Step - The serial number of the step - gets auto-populated once the workflow is saved and published.
  • Action - The activity involved. The action can be a request, submission, review, approval, etc. This is pre-populated from the chosen workflow template.
  • Company Type- The role of the contractor company in the project. This can be the general contractor, subcontractor, architect, etc.
  • Company Name- The business name of the company. You can choose the company from the respective drop-downs.
    • Click inside the 'Company Name' field and choose the company from the options.
  • Process Days- The maximum permissible days for the activity. The number of days allowed for each step is inherited from the respective values specified in the template by default. You can manually edit them as required. The 'Due Date' for each step auto-updates depending on the set process days. 
    • Double-click inside the 'Process Days' field to manually enter the number of days. 
  • In Date - The date on which the submittal was received for the action from the previous step.
  • Due Date - The target completion date of the activity. The date is auto-populated based on the completion date of the previous step and the allowed process days of the current step, excluding weekends and holidays. 
  • Out Date - The date on which the action was completed.
  • Status - Whether the action is complete, pending, or in processing.

  • Click 'Save' to apply the workflow to the submittal.
  • Click the 'Edit Workflow' button to change the assignee companies and/or the process days, if required. You cannot add or remove steps or change the sequence of actions by editing.

  • Click the Route button on the top right to forward the submittal to the next step.

You can view the status of the submittal in its workflow at any time by clicking the 'Workflow' tab.

Tip: You can chat with the team members and the participants of the submittal at any stage. Click the button on the top right. See Chat and Collaborate for more guidance.

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article