The RFI module allows the project managers of general contractors and subcontractors to perform the following actions:
General Contractor | Subcontractor | Architect/Engineer/Consultant |
Create RFIs | Create RFIs | Create RFIs |
Answer RFIs from their foremen or an SC PM | Review and forward or Reject RFIs created by their foremen | View details of RFIs assigned to them |
Set up a workflow sequence and choose the parties to respond/review/close the RFI in successive steps | Answer RFI created by their foremen | Answer/Review the RFIs that are assigned to them |
View details of RFIs assigned to them | Forward RFIs to the GC | Set up ad-hoc workflow steps for other stakeholders to 'Respond' or 'Review' for further clarifications |
Reject an RFI from their foreman or the PM of an SC, if they are trivial. | Close RFIs from their foremen | |
Set up ad-hoc workflow steps for other stakeholders to 'Respond' or 'Review' for further clarifications. | Answer the RFIs for which they are assigned as the responder | |
Review, approve, and close RFIs, after receiving responses from the assigned parties. | Set up ad-hoc workflow steps for other stakeholders to 'Respond' or 'Review' for further clarifications. |
Roles and Permissions: 1. All users in the project team, with appropriate permissions for the RFI module, can view, review, comment, or answer an RFI if their company is delegated as a responder/reviewer in the workflow. 2. Only users with 'Manage' permission can 'Route' the RFI to the next step. 3. Click 'Project' > 'My Team' > 'Members' > 'Workflow'to view the list of RFI workflow managers of the project.
The RFI Interface
- Ensure that you are in the management console of the project
- Click the app launcher , select 'Documents,'
- Click 'RFI' on the top.
The interface shows the project's RFIs under various stages. You can view and manage the RFIs in:
Boards View
The board view opens by default and shows the RFIs as cards under different stages. The items that are awaiting your response are indicated with the tag 'You' in blue.
- Click 'Boards' on the left to return to the Boards screen if you are already on a different screen in the RFI module
Stages:
- Draft - The RFIs created by you and yet to be routed.
- In Progress- RFIs routed and pending response.
General Contractor | Subcontractor | Architect/Engineer/Consultant |
|
|
|
|
|
|
|
|
- Answered - RFIs that have been created or routed by you, answered but waiting for approval, signature, or closure.
- Closed This Week - RFIs that were reviewed, approved, and closed by GC within the past seven days. RFIs that were closed before the past seven days can be viewed from the 'Closed' screen. See View and download RFIs for more details.
Each card shows the at-a-glance details of the RFI:
1 | - | The serial number of the RFI. |
2 | - | The title of the RFI. |
3 | - | The creation date of the RFI. |
4 | - | The criticality of the RFI. The priority is also indicated with color codes:
|
5 | - | The person/contractor company that raised this RFI. |
6 | - | The stakeholder with whom the RFI is awaiting a response currently. |
7 | - | The tag to indicate whether the RFI is awaiting your response |
8 | - | The classification of the RFI based on its purpose, whether the RFI is for clarification, confirmation, missing details in the specs/plans, etc. |
9 | - | The trade or division of work carried out by the contractor company that created the RFI. |
10 | - | The number of days remaining before the due date. For overdue RFIs, it shows the number of days past the due date.
|
11 | - | The date within which the RFI has to be closed. The due date from an RFI is calculated from the number of days permitted for each step in its workflow. For RFIs that are due shortly and overdue, the due date is highlighted to indicate the criticality.
|
12 | - | The status of the RFI.
|
- Click a card to expand the RFI.
You can review the question, reject it if it is trivial, set up a workflow, route it to the appropriate party, or answer it if assigned to you for a response, depending on your role in the workflow.
List View
- Click 'Log' on the left to open the RFIs in the list view
The list view shows the RFIs as a list with their details:
- RFI No - The serial number of the RFI
- RFI Name - The subject of the RFI. Click the name to open the RFI.
- Created On - The date on which the RFI was generated
- Created By - The contractor who generated the RFI
- Due By- The deadline date of the RFI. Due dates of RFIs that are imminent and overdue are indicated with color backgrounds.
- Yellow - Due within this week
- Red - Overdue. The due date has passed.
- Trade Type - The division of work to which the RFI pertains
- Priority- The criticality of the RFI. The priority level is also indicated by color codes:
- Red - High
- Orange - Medium
- Blue - Low
- RFI Type - The classification indicating the purpose of the RFI. Whether the RFI is for clarification, confirmation, missing details in the specs/plans, etc.
- RFI Sub Type - The further classification of the RFI, depending on the information requested.
- Status - The current progress stage of the RFI.
- Location - The location of the constructed structure for which clarification is needed.
- Specification Code - The section of the construction spec book that covers the category of tasks, deliverables, and/or materials to which the RFI relates.
- Schedule Impact - Whether the subject of the RFI affects the schedule of the project
- Cost Impact - Whether the subject of the RFI affects the budget or incurs extra expenses to the project.
- Sequence - The sequence number, depending upon the category of RFI in the master list created at your company level.
Search and filter options:
- Use the 'Search' box located at the top left to find RFI using any value from the table as search criteria
- The options at the top right allow you to filter the entries, create nested groups of entries, and manage personalized and customized views of the table. Use the links below to learn more about these:
Read the following sections to know more about:
Was this article helpful?
That’s Great!
Thank you for your feedback
Sorry! We couldn't be helpful
Thank you for your feedback
Feedback sent
We appreciate your effort and will try to fix the article