The foreman and the project manager of the assignee contractor company get notifications on assignments of the punchlist item. They can evaluate the item and decide to agree or dispute the work depending on the nature of the work. Once accepted, the field in-charge people like the site superintendent or the foreman can pull the items for resolution, assign crew members, and schedule them to work.
Accept a PLI to work
- Open the punch list tool on your mobile app
- Open the PLI in 'Open' state. You can do that in two ways:
1. From the 'Events' screen
- Open the event to view the list of items in it
- Tap the item you want to pull
2. From the 'Items' screen
- The items awaiting your action are listed in the 'Open' column
- Tap the item you want to pull
- Assess the item
- Tap 'Show Issue Location on PlanSheet' to view the spot
- Tap the attachments to expand them
- Tap 'Accept Work' to pull the work
The status of the item changes to 'Work Accepted.'
The next step is to assign crew members to resolve the issue.
Once the issue is fixed, you can mark the issue as resolved and notify the creator.
See the following page Execute a PLI Task to learn more.
Was this article helpful?
That’s Great!
Thank you for your feedback
Sorry! We couldn't be helpful
Thank you for your feedback
Feedback sent
We appreciate your effort and will try to fix the article