The scheduler allows you to add inspection events to the project schedule at any stage of work that requires site inspections and certifications by municipal and county authorities, site walk-throughs by the general contractor and the owner, periodical inspections by stakeholders, etc.
To add an inspection
- Navigate to the schedule page of the project
- Identify the row containing the schedule item after which you want to insert an inspection event
- Right-click on the row and choose 'Add' > 'Inspection' from the options
A new inspection row gets added at the same outline level as the row under which you created the event and is indicated with the icon :
By default, the duration is set to zero, and the date is set to the end date of the previous line item under which the event is included.
- Double-click inside the 'Task Name' cell and enter a label for the checkpoint
- Set the predecessor task for the inspection event. The start date is automatically set as the next day to the end date of the predecessor task. See Add dependencies for more details.
- Change the date for the inspection if required.
The inspection events are also shown in the Gantt chart view of the project schedule.
Was this article helpful?
That’s Great!
Thank you for your feedback
Sorry! We couldn't be helpful
Thank you for your feedback
Feedback sent
We appreciate your effort and will try to fix the article